ANALYSIS OF POWER TRANSFER ON TRANSMISSION CHANNELS 150 KV FROM GARDU INDUK AIR ANYIR TO GARDU INDUK SUNGAILIAT PLN BANGKA AREA
DOI:
https://doi.org/10.33019/ecotipe.v6i1.941Keywords:
Hyperbolic, Phase Angle, Power TransferAbstract
The availability of sufficient and quality electrical energy is a demand that must be fulfilled by PT. PLN (Persero). Distribution of electricity through the 150 kV transmission line with a relatively long distance and using aluminum type conductive wire always experiences changes in current and voltage, giving rise to the ability to send electricity power unstable. Other influences can also be obtained from changes in power factor and phase angle. The method used is the method of analyzing equations in the form of hyperbolis. In this study shows that the power transfer ability is influenced by phase angles. The maximum active power transfer capability is 1962.71 kW on VS which is 150∠75⁰ and VR which is 150∠0⁰ with phase angle difference is 75⁰. Whereas in VS = 150∠75⁰ and VR = 145∠0⁰ the transfer ability of active power is 1911.97 kW with the difference in the same phase angle of 75⁰. This study shows that the transfer ability of active power is influenced by voltage. The maximum active power transfer capability for VR values = 150∠0⁰ at VS which is constant, which is 150∠90⁰ is 2134.49 kW. Whereas for the VR value = 145∠0 VS at VS which is constant which is 150∠90⁰ is equal to 2078.03 kW.
Downloads
References
Cekdin, C. dan Barlian, T. (2013). Transmisi Daya Listrik. Andi Publisher, Yogyakarta.
Gonen, T. (1986). Electric Power Transmission System Engineering. Wiley Intersclence Publication, New York.
Hutauruk (1966). Transmisi Daya Listrik. Erlangga, Jakarta.
Irdha, Q. dan Maula, S. (2017). Pembatasan Transfer Daya Maksimum Dan Pemasangan Kapasitor Untuk Stabilisasi Tegangan. Jurnal JETri, Vol. 15, No. 1, Jakarta.
Kadir, A. (1998). Transmisi Tenaga Listrik. Universitas Indonesia (UI-Press), Jakarta.
Marsudi, Djiteng (2005). Pembangkitan Energi Listrik. Erlangga, Jakarta.
PLN Sektor Bangka. (2018). Single Line Diagram Transmisi Sistem Bangka. PLN Sektor Bangka: Buku Operasi Sistem, Bangka.
_________________. (2018). Data Transmisi Sistem Bangka. PLN Sektor Bangka: Buku Operasi Sistem, Bangka.
Stevenson, W. D. (1983). Analisis Sistem Tenaga Listrik. Erlangga, Jakarta.
Sujatmiko, H. (2009). Analisis Kerugian Daya Pada Saluran Transmisi Tegangan Ekstra Tinggi 500 kV di PT. PLN (Persero) Penyaluran dan Pusat Pengaturan Beban (P3B) Jawa Bali Regional Jawa Tengah dan DIY Unit Pelayanan Transmisi Semarang. Jurnal Teknik Elektro Vol. 1 No.1, Semarang.
Utari, I. (2017). Analisis Data Medan Magnet di Bawah Andongan Jaringan Transmisi SUTT 150 kV dengan Menggunakan Metode Bayangan. Jurnal Jurusan Fisika Fakultas Matematika dan Ilmu Pengetahuan Alam Universitas Sumatera Utara, Medan.
Downloads
Published
Issue
Section
License
Copyright in each article is the property of the author.
- The author acknowledges that the Jurnal Ecotipe (Electronic, Control, Telecommunication, Information, and Power Engineering) has the right to publish for the first time with a Creative Commons Attribution 4.0 International License.
- The author can enter the writing separately, regulate the non-exculsive distribution of manuscripts that have been published in this journal into other versions (for example: sent to the author's institution respository, publication into books, etc.), by acknowledging that the manuscript was first published in the Jurnal Ecotipe (Electronic, Control, Telecommunication, Information, and Power Engineering);